Week 1 – Introduction To Project Execution

 


1. What is project tracking?

Answers

·        A method for responding to project risks.

·        A method for assessing project successes and areas for improvement.

·        A method for following the progress of a project’s activities.

·        A method for reaching agreement among stakeholders on project scope.

Explanation: The process of monitoring and supervising the development of a project in order to guarantee that it is completed on time and without exceeding its allotted spending limit is referred to as "project tracking." Keeping an eye on tasks, deadlines, resources, and overall project milestones is often a part of it. The objective is to spot any possible problems at an early stage and then make any required modifications to ensure that the project stays on schedule. It is the equivalent of carrying a map with you and checking your GPS at frequent intervals to ensure that you are going in the proper direction.

2. Which five items should you track throughout the project execution phase?

Answers

·        Project costs

·        Key tasks and activities

·        Project goals

·        Progress toward milestones

·        Action items

·        Project schedule

3. Which tracking method is best for teams with a lot of people and projects with many tasks or milestones that are dependent on one another?

Answers

·        Roadmap

·        Project status report

·        Gantt chart

·        Burndown chart

Explanation: A Gantt chart is a strong tracking approach that may be useful for big teams and complex projects with several interdependent tasks. Gantt charts are a visual representation of the project schedule over time. They exhibit tasks, milestones, and the interdependencies between those elements in a style similar to a timeline. This makes it much simpler to comprehend the project's overall strategy and recognize and successfully manage essential routes and dependencies.

Gantt charts make it easy to see who is in charge of each task when those tasks are planned to begin and end, and how they are connected. This visual depiction helps coordinate efforts, manage resources, and make certain that activities that are reliant on one another are accomplished in the appropriate order.

Additionally, project management solutions that allow for collaborative editing and real-time updates may improve communication and coordination among big teams, making it simpler to monitor progress and respond expeditiously to any problems that may arise.

4. Which tool is most useful near the end of a project when meeting deadlines is the top priority?

Answers

·        Burndown chart

·        Roadmap

·        Gantt chart

·        Probability and impact matrix

5. Imagine that an aerospace company builds a new line of passenger jets. Increased raw material costs cause the company to spend more on aluminum than planned. Which of the triple constraints does this change impact the most?

Answers

·        Timeline

·        Scope

·        Budget

Explanation: In this instance, the increasing cost of aluminum has a direct influence on the financial component of the project, which may cause it to go beyond the budget that was originally anticipated. This modification may have a domino effect on other facets of the project, such as the distribution of resources, the timetables, and maybe even the scope, particularly if cost-cutting measures are adopted to maintain compliance with the financial plan.

6. Imagine a home improvement chain develops a new line of power tools. One of the designers wants to adopt a new process that will simplify the team’s workflow. Which method should they use to convey their idea to team members and stakeholders?

Answers

·        Gantt chart

·        Escalation email

·        Change request form

·        Risk register

7. Imagine that a toy company is known for making a popular doll, but their design team decides to test out a new material for the doll’s clothes before beginning a new batch. This test has what two types of dependencies?

Answers

·        External dependency

·        Discretionary dependency

·        Internal dependency

·        Mandatory dependency

8. What is the process of identifying risks and issues that could impact a project, and taking steps to address their potential effects?

Answers

·        Risk management

·        Dependency management

·        Project tracking

·        Escalation

Explanation: Risk management is the process of recognizing possible threats and problems within a project and then taking action to mitigate the potential consequences of such threats and problems.

9. What should you do in an escalation email? Select all that apply.

Answers

·        Explain the problem.

·        Make a request.

·        State your connection to the project.

·        Be serious and assert authority.

10. What can project managers do to keep trench war disagreements from bringing projects to a standstill?

Answers

·        Send an escalation email

·        Assess risk exposure

·        Apply the ROAM technique

·        Rely on the project roadmap

Explanation: For project managers, trench war disagreements—in which teams or stakeholders are entrenched in opposing views—can undoubtedly be a challenge.

11. Which of the following categories are part of the ROAM technique?

Answers

·        Restored, organized, allocated, and managed

·        Resolved, owned, accepted, and mitigated

·        Restored, organized, accepted, and managed

·        Resolved, owned, allocated, and mitigated

Shuffle Q/A 1

12. Project managers should track the details of their projects to be transparent and manage risks as they arise. What is another benefit of tracking in project management?

Answers

·        It decreases the overall cost of the project.

·        It helps the overall project stay on schedule.

·        It increases the number of tasks completed.

·        It keeps team members competitive.

Explanation: Accountability is yet another important advantage of using monitoring procedures in project management, joining the ranks of transparency and risk management.

13. A project manager closely tracks the hours and pay rate of a writer contracting on an ongoing project. What item are they tracking?

Answers

·        Project costs

·        Key tasks

·        Project schedule

·        Action items

Explanation: The costs that are related with the writer's services are being monitored by the project manager. To be more specific, they are keeping track of the number of hours worked by the writer as well as their compensation rate. This information assists in the management of the project's budget and ensures that the expenditures connected with the writer's services are in alignment with the project's overall financial strategy. The project manager is able to keep within the restrictions of the budget and make informed choices about the allocation of resources and the finances of the project thanks to the tracking of such information.

14. A stakeholder wants you to create a chart with a granular breakdown of each task and the time remaining to complete the tasks. What type of chart can you present to them?

Answers

·        Gantt chart

·        Project status report

·        Burndown chart

·        Roadmap

Explanation: A Gantt chart is an efficient tool that might be used to provide a detailed breakdown of each job as well as the amount of time that is still needed to finish them. Gantt charts provide a graphical depiction of project activities over the course of time, including the beginning and ending dates of each activity in the chart. They make it possible for stakeholders to see the order in which activities are to be completed, the lengths of those tasks, and how the tasks overlap or rely on one another.

You may offer a more in-depth perspective of the time that is still available for each job by using shading or color-coding to show elements of each task that have been finished, that are now being worked on, and that are still left. This enables the stakeholders to have a rapid understanding of the progress that has been made and the planned work for each particular assignment.

Because of their capacity to communicate intricate project timetables in a style that is both understandable and easy on the eyes, Gantt charts are quite popular in the field of project management. Because of this, they are a good option for displaying task breakdowns and the amount of time that is still available to stakeholders.

15. A burndown chart tracks time and amount of remaining tasks. What data is typically represented on the graph's X-axis, the horizontal axis?

Answers

·        Remaining time on the project

·        Remaining tasks on the project

·        Calculation of the sum of tasks

·        Assigned roles for the project

Explanation: The X-axis, often known as the horizontal axis, generally displays the passage of time on a burndown chart. It's a scale that displays the evolution of time throughout the project, and it's called a chronological scale. The beginning of the project is shown along the left side of the X-axis, while the completion of the project or a certain time period is shown along the right side.

On the Y-axis of the burndown chart is a time axis that depicts, in graphical form, how the number of jobs that are still outstanding is "burning down" as time passes. This offers a visual depiction of how well the project is tracking against its intended timeline and enables for a rapid evaluation of whether or not the team is on pace to accomplish the job within the period that was expected.

16. A software company builds an application to track employee satisfaction. The client wants to add three new features to the homepage of the application. Which of the triple constraints does this change impact the most?

Answers

·        Timeline

·        Scope

·        Budget

Explanation: In this instance, the incorporation of new features into the application results in the expansion of the scope of the project by the inclusion of new functionality. Because of this growth, the timetable and budget for the project may need to be adjusted in order to make room for the additional features' development, testing, and eventual deployment. It is very necessary to successfully manage scope adjustments in order to guarantee that the project will finish on schedule and within its budgetary constraints.

17. Which of the following methods can be used to communicate change to stakeholders during a project? Select all that apply.

Answers

·        Change request form

·        Project charter

·        Work breakdown structure

·        Escalation email

18. What should a project manager do first in order to incorporate dependency management into a project effectively?

Answers

·        Schedule regular meetings with the team members

·        Create a risk register for the dependencies

·        Identify all possible dependencies and categorize them

·        Communicate updates with stakeholders

19. Imagine that a project manager creates a matrix with two variables: risk impact and probability. They use the matrix to measure potential future losses to a project resulting from specific activities or events. What is the project manager trying to determine?

Answers

·        Risk management

·        Risk dependencies

·        Risk exposure

·        Risk appetite

Explanation: A Risk Impact and Probability Matrix is being used by the project manager in order to evaluate and rank the various hazards associated with the project.

20. Three team members on your project cannot agree on an implementation for a key task. How can you ensure a decision is made in time?

Answers

·        Adjust the timeline for the project due to the delay

·        Escalate the question to leadership for feedback

·        Make a guess to the best of your knowledge and implement

·        Give the team members more time to make a decision

21. How can escalation benefit a project? Select all that apply.

Answers

·        Makes external dependencies trackable

·        Speeds up decision-making

·        Provides checks and balances

·        Encourages team participation

22. Imagine you are managing a project that hits a major milestone early, putting the team ahead of schedule. This alters the project plan’s original course of action. What is the name for this type of event?

Answers

·        A risk

·        A deviation

·        An issue

·        A reset

Explanation: When a project reaches a significant milestone ahead of schedule, it is often referred to as having a "positive variance" or having a "early completion." This is because it changes the initial course of action that was outlined in the project plan. This indicates that the project has advanced more swiftly than was first expected, which may have a variety of positive consequences including possible prospects for additional optimization, cost savings, and greater stakeholder satisfaction. It's a change from the original idea that goes in a more successful path overall.

23. What should project managers track to ensure the team meets deadlines?

Answers

·        Track costs to avoid over- or under-spending on project activities.

·        Track stakeholder engagement to ensure they are aligned on project goals.

·        Track tasks as they progress and as the project approaches key milestones.

·        Track project successes and celebrate achievements with the team.

24. Which tracking method is most useful when project managers need a way to track big milestones in a project?

Answers

·        Gantt chart

·        Project status report

·        Roadmap

·        Burndown chart

Explanation: It's possible that a Milestone Chart or a Milestone Schedule may prove to be the most helpful monitoring approach for project managers who need to keep tabs on significant project milestones. A Milestone Chart is a graphical depiction that draws attention to important milestones or accomplishments along the path of a project's timetable. It makes it much simpler to monitor progress and convey that status to various stakeholders since it presents a perspective of critical milestones that is both clear and focused.

Shuffle Q/A 2

25. Imagine that a client wants to add an auction of donated items to a fundraising event. The project manager is currently executing the project for a dinner and short concert. Which of the triple constraints does this change impact the most?

Answers

·        Timeline

·        Budget

·        Scope

Explanation: When a project manager is originally executing the project for a dinner and brief concert, adding an auction of donated goods to a fundraising event would largely effect the scope constraint of the triple constraints in project management. This is because adding an auction would increase the number of tasks that need to be completed.

26. You brainstorm with your team members to identify and list the events that might delay the project. What type of document are you creating in this scenario?

Answers

·        Impact Matrix

·        Risk register

·        Task List

·        Risk Matrix

Explanation: You are in the process of putting together a Risk Register or a Risk Log at the moment. Within the context of project management, a Risk Register is a record that is used for the purpose of methodically identifying, evaluating, and documenting any risks that may have an effect on the project.

27. During a project you are managing, a major disaster shuts down the design facility. What is this type of event called?

Answers

·        A start

·        A risk

·        A deviation

·        An changelog

Explanation: The occurrence of a significant catastrophe during the course of a project that results in the closure of the design facility is often referred to as an act of force majeure or an act of God. The phrase "force majeure" is a legal word that is used to describe events that cannot be predicted and are beyond the control of the parties concerned. These types of events include natural catastrophes, war, strikes, and other unusual occurrences.

In the management of projects, unforeseen circumstances known as "force majeure" may have a substantial influence on the project's timeframe, resources, and final products. Even while project managers often integrate contingency planning and risk management measures to mitigate the possible consequences of such occurrences, the occurrence of such events may still provide obstacles that call for prompt and adaptable reactions.

28. What item should you track during the project execution phase to ensure the project successfully moves towards its completion date?

Answers

·        Retrospective notes

·        Team performances

·        Project proposal 

·        Project schedule

Explanation: During the period in which the project is being put into execution, one of the most important things to monitor in order to guarantee that the project will be finished on time is the progression of its tasks and milestones. A real-time perspective of the degree to which a project is following to the schedule that was specified may be obtained by monitoring the accomplishment of specific tasks and milestones.

29. You manage a project with multiple milestones dependent on each other. One team must hit these milestones before another team can begin their tasks. What type of chart can you use to track this project?

Answers

·        Roadmap

·        Burndown chart

·        Project status report

·        Gantt chart

Explanation: When there are several milestones that are interdependent on one another, a Gantt chart may be an extremely useful tool for monitoring and visually representing the project timeline as well as the interdependencies between the milestones.

30. How does a roadmap differ from a burndown chart?

Answers

·        A roadmap tracks big milestones and includes a high-level project overview; a burndown chart measures time against the amount of work completed and remaining.

·        A roadmap is useful for large projects with many dependencies; a burndown chart tracks big milestones and includes a high-level project overview.

·        A roadmap tracks big milestones and includes a high-level project overview; a burndown chart is useful for large projects with many dependencies.

·        A roadmap measures time against the amount of work completed and remaining; a burndown chart tracks big milestones and includes a high-level project overview.

Explanation: Both a roadmap and a burndown chart serve distinct functions within the context of project management; however, these functions are neither served by the same information nor by the same layout.

31. During a project’s execution phase, what type of event does scope creep signify?

Answers

·        Milestone

·        Task

·        Concern

·        Risk

Explanation: The execution phase of a project is known as the "scope creep" phase because it is during this phase that extra features, tasks, or requirements are added to the project without the required appraisal, approval, or corresponding modifications being made to the project plan. It is a term that refers to the unchecked growth of a project's scope beyond the bounds it had originally set.

The introduction of new features, modifications to the requirements, or the incorporation of extra deliverables that were not previously envisaged may all be examples of scope creep. Scope creep can also take on a variety of other forms. This phenomena has the potential to have substantial repercussions for the project, including higher costs, the possibility of delays, and difficulties in the management of the resources.

During the period of execution in which the project is being carried out, it is essential to prevent the expansion of the project's scope. It requires keeping a careful eye on changes, determining how those changes will affect the project's schedule and finances, and getting official clearance for such modifications before adopting them into the scope of the project. It is very necessary to have communication and change control mechanisms that are effective in order to reduce the risks associated with scope creep.

32. Imagine that a restaurant is moving to a new location and must pass a government health inspection before it can open. What type of dependency is the inspection? Select all that apply.

Answers

·        External dependency

·        Mandatory dependency

·        Discretionary dependency

·        Internal dependency

Explanation: This kind of dependence occurs often in circumstances in which one activity or job has to be finished before another can begin, and it is especially obvious in circumstances requiring regulatory or compliance requirements, such as health inspections in the case of a restaurant.

33. What tool can project managers use to calculate risk exposure and prioritize risks using high, medium, and low rankings?

Answers

·        Probability and impact matrix

·        Mitigation plan

·        Risk register

·        ROAM technique

Explanation: The risk exposure of a project may be calculated with the use of a Risk Matrix or a Risk Assessment Matrix, and the risk can then be prioritized according to its high, medium, or low rating. The Risk Matrix is a graphical instrument that assists in assessing and classifying hazards according to their degree of probability and effect.

34. Which term refers to the process of enlisting leadership or management to remove an obstacle, clarify or reinforce priorities, and validate next steps?

Answers

·        Escalation

·        Risk management

·        Elevation

·        Risk exposure

Explanation: Escalation is a term that is typically used to describe the act of soliciting the help of leadership or management in order to eliminate an impediment, clarify or reinforce goals, and validate the next steps. When a problem or worry at the present level of authority or management cannot be handled, the problem or concern might be escalated to higher levels of authority or management. This is done in order to get more assistance, decision-making, or intervention in order to overcome hurdles and make certain that the development of the project fits with corporate objectives. Escalation is a tactical method that may be used to solve problems that can prevent the project from being successful.

35. During the project, two members of your team settle on a decision for the project, which will negatively impact the project outcome. What issue does this represent?

Answers

·        Risk appetite

·        Bad compromises

·        Trench wars

·        Mid agreement

Explanation: An problem with inadequate cooperation or decision-making within the team is represented by a circumstance in which two members of your team settle on a choice for the project that will adversely effect the result of the project.

36. As a project manager, you’re implementing the ROAM technique for a new risk. You work with stakeholders and team members to formulate a plan to lessen the impact the risk will have on the project. Which ROAM category is this risk now in?

Answers

·        Resolved

·        Owned

·        Accepted

·        Mitigated

Explanation: In the risk management strategy known as ROAM (which stands for Resolve, Own, Accept, and Mitigate), the category known as Mitigate is assigned to a risk after a plan has been developed to reduce the negative effects of a risk. The process of mitigating a risk is adopting preventative measures to lessen its likelihood or the impact it may have, hence limiting the risk's potential adverse impacts on the project.

37. Why should project managers track changes, dependencies, and risks throughout a project?

Answers

·        Keep teams aligned on how to ensure project success

·        Determine who made tracking mistakes during the retrospective

·        Help prepare for the next project

·        Demonstrate the importance of accepting change

Shuffle Q/A 3

38. Which tool provides an overview of a project’s common elements, summarizes them as a snapshot, and communicates project status to the team and stakeholders in a centralized place?

Answers

·        Gantt chart

·        Burndown chart

·        Project status report

·        Roadmap

Explanation: Providing an overview of a project's common features, summarizing those elements in the form of a snapshot, and communicating the project status to the team and stakeholders in one centralized location are the primary functions of a tool known as a project dashboard. The dashboard often consists of key performance indicators (KPIs), metrics, and visual representations of project progress. This provides stakeholders with the ability to rapidly evaluate the health of the project as well as its performance. Throughout the duration of the project's lifespan, it acts as a consolidated information hub that can be accessed easily, hence facilitating more efficient communication and decision-making.

39. A team starts a new project to launch a website. The first task is to create the designs of the webpage. The second task is to develop the web pages based on the designs. What type of dependency does this indicate?

Answers

·        Discretionary dependency

·        External dependency

·        Mandatory dependency

·        Internal dependency

40. Under what conditions should you send an escalation email? Select all that apply.

Answers

·        Key stakeholders need to sign off on a final decision.

·        A problem inconveniences the core project team, but they resolve it themselves.

·        A project team member identifies a potential risk that may have an impact in several months.

·        A problem leads to major changes in budget or timeline.

41. What common problems can a project manager avoid by escalating an issue? Select all that apply.

Answers

·        Trench wars

·        Risk appetite

·        Force majeure

·        Misdirected compromises

42. In the ROAM technique, what does it mean to resolve a risk?

Answers

·        To classify a risk as addressed because it no longer creates a problem

·        To give a team member ownership over a certain risk and entrust them to handle it

·        To understand and accept a risk for what it is because it cannot be resolved

·        To reduce the impact of a risk or the likelihood the risk will occur

Explanation: Within the context of the ROAM method, "Resolve" refers to the measures that are done to actively address and get rid of a particular risk. When a risk is labeled as "Resolve," it means that the team working on the project has made the decision to take prompt and final action in order to entirely remove or reduce the risk. The possible negative influence that the risk might have on the project has to be eliminated, the risk's probability needs to be reduced, and the project's repercussions need to be minimized to a level that is acceptable.

Implementing certain actions or methods with the goal of eliminating a risk entirely or considerably reducing both its likelihood and its effect is required in order to resolve a risk. This can include making adjustments to the project's plans, procedures, resources, or any number of other pertinent components that directly address the risk that was discovered.

The process of resolution is often exhaustive, and it necessitates the creation of a comprehensive strategy, in order to guarantee that the risk is successfully mitigated and that the project may go forward with less uncertainty. The end goal is to get to a position when the risk is no longer a major obstacle in the way of completing the project successfully.

43. As a project manager, you regularly send progress reports out to team members and stakeholders. These reports make the project progress transparent to all involved. What project management activity could these progress reports be a part of?

Answers

·        Assessing Risks

·        Tracking

·        Resetting

·        Documenting

Explanation: As part of the activity referred to as Communication Management, you will be responsible for providing stakeholders and members of your team with frequent updates on the status of the project. The process of designing, carrying out, and monitoring the flow of information on a project between all of its many stakeholders is referred to as "communication management."

44. What type of chart will you create to represent tasks with multiple dependencies?

Answers

·        Roadmap

·        Gantt chart

·        Probability and impact matrix

·        Burndown chart

Explanation: Creating a Network Diagram or a Dependency Diagram is the standard procedure for representing activities that include several dependent relationships.

A Network Diagram is a graphical representation of the connections and interdependencies that exist between the many activities that comprise a project. This kind of diagram offers a distinct and specific picture of the logical progression of activities as well as the order in which tasks should be completed.

45. A software company builds an application to track employee satisfaction. A contractor delays the completion of a key task. Which of the triple constraints does this change impact the most?

Answers

·        Scope

·        Timeline

·        Budget

Explanation: The time component of the triple constraints in project management is negatively impacted when a contractor takes too long to finish one of the most important tasks in the process of developing an application to assess employee happiness.

46. When writing an escalation email, you open the email with “I hope you all had a great, long weekend.” Which of the five keys to writing a strong escalation email is this an example of?

Answers

·        Maintain a friendly tone

·        Explain the consequences

·        Make a request

·        Explain the issue

Explanation: The phrase "I hope you all had a great, long weekend" is an example of the "Softening" key to crafting a powerful escalation email. This introductory line is used in an escalation email.

Before addressing the primary problem or concern, softening includes beginning the email with a tone that is either positive or neutral in order to establish an environment that is more receptive. It helps build a courteous and collaborative tone, which increases the likelihood that the receivers will be receptive to the information that is being delivered in the escalation, which is a positive outcome for everyone involved. During the escalation process, this strategy is very helpful in maintaining a constructive and professional communication style with all parties involved.

47. Which of the following items should a project manager include in a change request form for a project team? Select all that apply.

Answers

·        Teams involved

·        Retrospective summary

·        Project name

·        Original project proposal

48. Which of the following steps are part of dependency management? Select all that apply.

Answers

·        Continuous monitoring and control

·        Recording dependencies

·        Eliminating dependencies

·        Efficient communication

49. What tool can project managers use to calculate risk exposure and prioritize risks using high, medium, and low rankings?

Answers

·        Probability and impact matrix

·        Risk register

·        ROAM technique

·        Mitigation plan

Explanation: The risk exposure of a project may be calculated with the use of a Risk Matrix or a Risk Assessment Matrix, and the risk can then be prioritized according to its high, medium, or low rating. A Risk Matrix is a graphical tool that assists in the assessment and classification of risks according to the probability and effect of such hazards.

50. When writing an escalation email, you describe how the current obstacle will delay the project in the next phase. Which of the five keys to writing a strong escalation email is this an example of?

Answers

·        Make a request

·        Explain the consequences

·        Maintain a friendly tone

·        Explain the issue

Explanation: An example of the "Impact" key to creating a powerful escalation email would be to describe how the present impediment would delay the project in the following phase inside an escalation email. This would be an example of a "Impact" key.

It is helpful to explain the importance and repercussions of the current hurdle by highlighting its effect. This gives stakeholders a clear picture of how the obstacle impacts the project's timeframe, milestones, or overall success. highlighting the impact also helps convey the relevance of the current obstacle. This information is essential for decision-makers, since it allows them to evaluate how urgent the situation is and rank the activities that need to be taken in order to successfully overcome the barrier.

51. Two team members in your project cannot seem to come to an agreement on a new design feature. What common issue does this represent in project management?

Answers

·        Bad compromises

·        Trench wars

·        Risk appetite

·        Trade-off agreement

Explanation: When two members of a team are unable to reach a consensus on a new design element, it is an example of a typical problem in project management that is referred to as Conflict or Disagreement. When people have different ideas, points of view, or preferences on certain parts of the project, such as design choices, techniques, or decisions, it may lead to conflict.

52. In the ROAM technique, what does it mean to accept a risk?

Answers

·        To reduce the impact of a risk or the likelihood the risk will occur

·        To give a team member ownership over a certain risk and entrust them to handle it

·        To classify a risk as addressed because it no longer creates a problem

·        To agree nothing will be done about a risk

Explanation: Oh, the good old ROAM method! This is a very useful instrument for risk management. When you accept a risk in ROAM, it indicates that you are aware of it but do not have any concrete plans in place to eliminate or reduce the negative effects of the risk. It's comparable to declaring "Yep, we know this could happen, and we're willing to deal with the consequences if it does." It all comes down to being aware of the situation and making an educated choice about how to deal with a certain danger.

53. During the execution phase, an issue arises that will cause the project's costs to overrun the budget. How can the project manager address the issue?

Answers

·        Ask your team to work more hours to meet timelines

·        Document the issue and move forward

·        Make a mental note to discuss in the retrospective

·        Escalate the issue to leadership

54. As a project manager, you ensure the team is accomplishing the necessary tasks to hit target dates along the way. What item are you tracking?

Answers

·        Progress towards milestone

·        Team members planned PTO

·        Project proposal

·        Stakeholder options

Explanation: In this kind of situation, you would probably be monitoring the timetable or schedule of the project. In order to verify that the team is making the progress that was anticipated, it is necessary to maintain a constant check on the tasks, milestones, and deadlines. Monitoring the schedule of the project enables you to recognize possible delays at an earlier stage, which in turn enables you to take corrective steps to ensure that the project remains on track. It entails monitoring the start and finish dates of activities, the relationships between tasks, and the overall status of the project in comparison to the schedule that was established. You will be able to proactively address any problems that may crop up and make modifications in order to guarantee that the project achieves its goal dates if you do this.

55. During the project execution phase, what chart can you use to illustrate how a project should evolve over time to your stakeholders and team members?

Answers

·        Burndown chart

·        Roadmap

·        Project status report

·        Gantt chart

Explanation: The reliable Gantt chart has come through for us this time! During the execution phase of a project, a Gantt chart is an excellent visual tool for displaying how a project should go over the course of time. It offers a timeline view of tasks, milestones, and dependencies, making it possible for stakeholders and members of the team to understand at a glance the schedule that has been set. Each activity is shown on the timeline as a horizontal bar, with the length of the bar indicating how long it will take to complete and the location of the bar on the timeline showing when it will be carried out.

The communication of the project schedule, the display of the sequence of work, and the marking of significant milestones are all excellent uses for Gantt charts. They assist everyone who is participating in the project in better comprehending the timeframe, the interdependence between tasks, and the overall progress. In addition to that, they are quite pleasing to the eye.

56. How does a change request form differ from an escalation email?

Answers

·        Change request forms help teams manage proposed changes; escalation emails enlist leadership to remove obstacles, reinforce priorities, and validate next steps

·        Change request forms enlist leadership to manage proposed changes; escalation emails help teams remove obstacles, reinforce priorities, and validate next steps

·        Change request forms help teams remove obstacles, reinforce priorities, and validate next steps; escalation emails enlist leadership to manage proposed changes

·        Change request forms enlist leadership to remove obstacles, reinforce priorities, and validate next steps; escalation emails help teams manage proposed changes